One-year construction update at CMH - May 2024
We're a year into Phase 1 of the expansion at Cariboo Memorial Hospital in Williams Lake. Senior project manager Brad Mackendrick outlines where the project is at and how far...Read more
CMH Redevelopment Update – December 2025
At the end of 2025, we've nearly completed the exterior of the building and interior flooring and ceiling installation is well underway. The expanded hospital is expected to be open to patients early 2027.
CMH Redevelopment - August 2024 Update
Construction continues to progress at Cariboo Memorial Hospital and we've reached the third storey in summer 2024. This level will be home to the new medical unit.