Cariboo Memorial Hospital
Cariboo Memorial Hospital Redevelopment Project
The Cariboo Memorial Hospital redevelopment project is underway and over the next three to six years, people in Williams Lake and the Cariboo-Chilcotin will benefit from this modernized and expanded hospital.
Interior Health is excited to share information about this project as it proceeds and update the community on potential impacts based on the construction schedule. The CMH redevelopment project includes an addition to the existing hospital as well as renovations to the existing facility.
- Phase 1, which includes the addition, began in April 2023 and is expected to be complete in late 2026.
- PhaseContinue reading
Cariboo Memorial Hospital Redevelopment Project
The Cariboo Memorial Hospital redevelopment project is underway and over the next three to six years, people in Williams Lake and the Cariboo-Chilcotin will benefit from this modernized and expanded hospital.
Interior Health is excited to share information about this project as it proceeds and update the community on potential impacts based on the construction schedule. The CMH redevelopment project includes an addition to the existing hospital as well as renovations to the existing facility.
- Phase 1, which includes the addition, began in April 2023 and is expected to be complete in late 2026.
- Phase 2, which includes renovations to the existing hospital, is planned to begin in fall 2026 and is scheduled to be complete in early 2029.
People will have increased access to health-care services as the expanded hospital will include:
- A new emergency department with 23 treatment spaces, an increase of 12; two trauma treatment bays; two specialized procedure rooms; an ambulance carport; and a separate public entrance.
- A new medical/surgical inpatient unit with 36 beds, an increase of 16.
- A new mental health and substance use inpatient unit with eight single-occupancy rooms.
- An expanded ambulatory care and oncology unit with 16 renovated treatment spaces.
- An expanded maternity and women's health unit with four single-occupancy rooms for maternity care, two nursery rooms and two women's health beds in private rooms. The maternity area will allow parents to stay in the same room with their babies until they are ready to go home.
- An expanded pharmacy, providing additional space for pharmacists and pharmacy technicians.
- An interfaith sacred space for traditional cultural and healing practices.
- Smudging in patient rooms.
- 71 new parking stalls.
- A new UBC Faculty of Medicine academic space.
-
One year of construction at CMH
Share One year of construction at CMH on Facebook Share One year of construction at CMH on Twitter Share One year of construction at CMH on Linkedin Email One year of construction at CMH link -
Construction Crane
Share Construction Crane on Facebook Share Construction Crane on Twitter Share Construction Crane on Linkedin Email Construction Crane linkThe construction crane went up at CMH on Dec. 7-8. The crane towers 200-feet tall and another 200-feet wide and is lit up with Christmas lights at night. It is expected to be in Williams Lake for about eleven months.
The Williams Lake Tribune was on site for a tour in December. Read their story.
-
Construction starts on Cariboo Memorial Hospital project
Share Construction starts on Cariboo Memorial Hospital project on Facebook Share Construction starts on Cariboo Memorial Hospital project on Twitter Share Construction starts on Cariboo Memorial Hospital project on Linkedin Email Construction starts on Cariboo Memorial Hospital project linkHealth Minister Adrian Dix visited Williams Lake on Tuesday, July 4 to celebrate the beginning of construction on the redevelopment of Cariboo Memorial Hospital with President and CEO Susan Brown and local community representatives.
The project includes a three-storey addition, as well as renovations to the existing facility. The redevelopment will add 25 new beds for a total of 53. This includes a new medical/surgical inpatient unit with 36 beds (an increase of 16), a new mental-health and substance-use inpatient unit with eight single-occupancy rooms, a patient-seclusion room and an expanded ambulatory-care and oncology unit with 16 renovated treatment spaces.
There will be a new emergency department with 23 treatment spaces (an increase of 12), two trauma-treatment bays, a seclusion room, an ambulance carport and a separate public entrance.
The new addition will also have an expanded maternity and women’s health unit with four single-occupancy rooms for maternity care, two nursery rooms and two women’s health beds in private rooms. The maternity area will allow parents to stay in the same room with their babies until they are ready to go home.
The pharmacy will be expanded, providing additional space for pharmacists and pharmacy technicians. An interfaith sacred space will allow for traditional cultural and healing practices. There will be 71 new parking stalls.
Construction will happen in two phases. The first phase, which will include the three-storey addition, is expected to finish in 2026. Phase 2 will start after that, will include further renovations and is scheduled to be complete in 2029.
Signup Banner
Project Progress Photos
Videos
-
Click here to play video CMH Redevelopment - August 2024 Update Construction continues to progress at Cariboo Memorial Hospital and we've reached the third storey in summer 2024. This level will be home to the new medical unit.
-
Click here to play video One-year construction update at CMH - May 2024 We're a year into Phase 1 of the expansion at Cariboo Memorial Hospital in Williams Lake. Senior project manager Brad Mackendrick outlines where the project is at and how far we've come in the last 12 months.
-
Click here to play video Williams Lake First Nation blessing ceremony - July 2021 The Williams Lake First Nation held a blessing ceremony for the Cariboo Memorial Hospital Redevelopment Project in Williams Lake, July 2021.
Timeline
-
February 2018
Cariboo Memorial Hospital has finished this stageConcept Planning Approved
-
July 2019
Cariboo Memorial Hospital has finished this stageBusiness Plan Approved
-
April 2021
Cariboo Memorial Hospital has finished this stagePreferred Proponent Selected
-
February 2023
Cariboo Memorial Hospital has finished this stageConstruction Contract Signed
-
April 2023
Cariboo Memorial Hospital is currently at this stageConstruction Phase 1
-
Fall 2026
this is an upcoming stage for Cariboo Memorial HospitalConstruction Phase 2
-
2029
this is an upcoming stage for Cariboo Memorial HospitalOpen to Patients